Catalogue specification image for the JY9801-600-20oz PET cup
The catalogue product image was restored with AI to help identify the model. A schedule should name the cup model, such as this JY9801-600-20oz catalogue reference, and the artwork version. The product image does not establish printing approval, production duration or delivery dates.

A dated example: the later sample condition controls the start

Suppose the final artwork is approved on 2 November 2026, but WJPETCUP receives the sample payment on 5 November. Both conditions are complete only on 5 November. Sending the artwork earlier or initiating a payment transfer is not the same as completing the two required conditions.

For this illustration, treat the date on which both conditions are met as day 0. Seven calendar days after 5 November is 12 November; ten calendar days after it is 15 November. Calendar days include weekends. The dates below illustrate the counting method, not an actual order commitment; record the agreed dated sample milestone for your own order.

Illustrative sample production dates — not sample delivery dates
MilestoneExample dateMeaning
Final artwork approved2 November 2026One of the two start conditions is complete
Sample payment received5 November 2026The second condition is complete; day 0 in this example
Day 712 November 2026Seven calendar days after the illustrated start
Day 1015 November 2026Ten calendar days after the illustrated start
Sample received and reviewedNot assignedSample transport and buyer review need separate dates

Leave space for the sample to reach a decision

The 7–10-day period does not include an assumed journey to the buyer or a fixed buyer review period. Record how the sample will be sent, when the buyer expects to receive it and who will review it. A sample that has arrived but has unresolved artwork comments has not yet produced a final buying decision.

Use the sample record to distinguish accepted items, requested revisions and unresolved questions. If another sample may be needed, keep that possibility visible in the plan. Do not add an invented standard revision period or presume that every change automatically requires the same work.

Build the bulk plan from the payment and quoted duration

For the bulk order, record the date WJPETCUP receives the initial payment and the production duration confirmed for the actual quantity. The sample period must not be substituted for that duration. The model mix and quantities should be explicit so that a schedule for one order is not reused for another.

Next distinguish production completion from dispatch and arrival. A production completion date alone does not specify when transport starts. Record any agreed interval between completion and dispatch, then the transit estimate and the destination point it covers.

Variables needed before a bulk arrival date can be calculated
SymbolValue to establishKeep it separate from
PDate the bulk initial payment is receivedDate the buyer initiates payment
BProduction duration agreed for the actual orderThe 7–10-calendar-day printed sample period
HAny agreed interval from production completion to dispatchTransit after dispatch
TTransit estimate to the agreed destination pointUnspecified onward delivery or handling
RBuyer's required arrival date at that pointA requested factory completion or dispatch date

Work backwards without inventing the missing durations

For a simple planning model in which these stages follow one another, the arrival estimate is P + B + H + T. Working backwards from the required arrival date gives a target payment-receipt date of R minus T minus H minus B. This is a planning relationship, not a confirmed manufacturing schedule.

Only apply that arithmetic once the durations, their units and the date-counting conventions have been agreed. A production quotation expressed in working days cannot simply be treated as calendar days. If B or T is still unknown, leave the corresponding target date unresolved instead of filling it with a typical industry lead time.

Compare the resulting target with the sample decision plan. If your buying process requires sample approval before proceeding, that decision must be available in time for your planned order steps. State that as your planning requirement; do not infer an additional WJPETCUP production-start rule beyond the confirmed initial-payment condition.

When a condition moves, update the affected dates

Return to the sample illustration. If final artwork approval occurs on 8 November instead of 2 November, while payment is still received on 5 November, day 0 becomes 8 November. Using the same illustrative counting method gives 15–18 November for days 7–10. This is a later first approval, not a claim that artwork changes after work begins always restart a fixed clock.

If the artwork changes after sampling has started, ask what work must be repeated and obtain a revised dated milestone. If the order quantity changes, obtain the applicable bulk duration. If the destination or transport arrangement changes, revisit the transit scope and estimate. Preserve the earlier plan so that the reason for the revision remains clear.

A buyer can include contingency time in an internal plan, but it should be labelled as the buyer's allowance. It is not a supplier promise and should not hide an unresolved production or transport period.

Finish with one schedule tied to one order version

Keep the model list, quantity per model, artwork revision, sample start dates, review status, bulk payment receipt and agreed production and delivery milestones together. The useful output is a dated record with owners for open questions, rather than a single number labelled 'lead time'.

Before relying on the arrival estimate, check that the quotation and schedule still describe the same order. WJPETCUP's minimum is 5000 pieces per PET model, including PET printing orders; quantities from different models cannot be combined to meet it. That minimum does not determine sample quantity or the duration of a bulk order.

Read more

Request dates for a defined order

Send the exact models, quantity per model, artwork revision, destination and required arrival date. Identify which sample decisions are complete so that production and transport milestones can be discussed separately.